mark1447 Posted March 29, 2012 Share #351 Posted March 29, 2012 Here are the upcoming dates (As per a G/O. photo of a poster I saw from a friend) IRT 7th Avenue: (34th-Atlantic) April 9-13, June 25-29, October 15-19 IRT Lexington Avenue: (42nd-Atlantic) June 11-15, Sept. 3-7, November 5-9 IND 6th Avenue: (59th-W4th) May: 14-18, July: 23-27, Sept. 24-28 IND 8th Avenue: (59th-WTC & Jay) April 23-27, July 9-13, October 22-26 Link to comment Share on other sites More sharing options...
TwoTimer Posted March 31, 2012 Share #352 Posted March 31, 2012 The idea with the FASTRACK work is to get it done quicker, and safer instead of "piecemeal" jobs throughout the weekends and overnight hours with full flagging. For the rider as far as service quality, it means less weekend and overnight flagging (there's still some overnight flagging as catchup with all the lack of maintenance will take awile, but I expect a difference in the amount of flagging overnights/weekends eventually). Right now, they want to properly light the tunnels (one of the more noticable features), as some places are completely dark, while others are using inefficient incandescent bulbs. The 8Av and 6Av river tubes are now ablaze in light, and I assume the Lex and 7Av are as well. Link to comment Share on other sites More sharing options...
Guest Lance Posted April 1, 2012 Share #353 Posted April 1, 2012 As part of the ongoing FasTrack project, from April 7th to the 16th, there will be no Manhattan-bound E- or F-line service at Sutphin Blvd (Hillside only), Briarwood-Van Wyck Blvd and 75 Av. Manhattan-bound trains will run express between Parsons Blvd or Jamaica-Van Wyck and Forest Hills-71 Av at all times during this service change. Link to comment Share on other sites More sharing options...
GojiMet86 Posted April 1, 2012 Share #354 Posted April 1, 2012 Interesting. For a line with no parallel line, it seems it is going to be one direction at a time. Link to comment Share on other sites More sharing options...
pjbr40 Posted April 1, 2012 Share #355 Posted April 1, 2012 Lance are you April Fooling us? Link to comment Share on other sites More sharing options...
Mysterious2train Posted April 1, 2012 Share #356 Posted April 1, 2012 It's for real. It's on the 's site. And this G.O. is only at night, just like FastTrack. http://travel.mtanyc...thod=getstatus4 Link to comment Share on other sites More sharing options...
mark1447 Posted April 2, 2012 Share #357 Posted April 2, 2012 As part of the ongoing FasTrack project, from April 7th to the 16th, there will be no Manhattan-bound E- or F-line service at Sutphin Blvd (Hillside only), Briarwood-Van Wyck Blvd and 75 Av. Manhattan-bound trains will run express between Parsons Blvd or Jamaica-Van Wyck and Forest Hills-71 Av at all times during this service change. This is not a Fastrack G/O as the never mention Fastrack. Thats just a standard G/O. And what reason is this being done? Link to comment Share on other sites More sharing options...
NX Express Posted April 2, 2012 Share #358 Posted April 2, 2012 That GO is actually at all times - checking the timing, the never stops at those stations in that date range. Link to comment Share on other sites More sharing options...
TwoTimer Posted April 2, 2012 Share #359 Posted April 2, 2012 No Manhattan-bound service at Briarwood-Van Wyck Blvd and 75 Av Weeknights & Weekends, 12:01 AM Sat, Apr 7 to 5 AM Mon, Apr 16 For service from these stations, take the * or to Union Tpke or the * to Jamaica-Van Wyck and transfer to a Manhattan-bound . For service to these stations, take the to Union Tpke or 71 Av and transfer to a Jamaica Center-bound * or Jamaica-bound . *Jamaica Center-bound service is not available at these stations Mon to Fri, 7:30 AM to 7:30 PM. Note: Manhattan-bound trains also skip these stations during this time. Link to comment Share on other sites More sharing options...
Guest Lance Posted April 2, 2012 Share #360 Posted April 2, 2012 This is not a Fastrack G/O as the never mention Fastrack. Thats just a standard G/O. And what reason is this being done? I dropped it in the FASTRACK thread because the MTA clumped it together with the usual FASTRACK reroutes in its committee presentation last November. http://www.mta.info/...osure111114.pdf - go to page 13 in the .pdf file. Link to comment Share on other sites More sharing options...
TwoTimer Posted April 2, 2012 Share #361 Posted April 2, 2012 An odd piece of journalism but ok. I guess I should submit my letter again for technical writing. Link to comment Share on other sites More sharing options...
pjbr40 Posted April 5, 2012 Share #362 Posted April 5, 2012 Lucky the fast track for 1, 2, 3, didn't happen this week. I wander what happen if tons of worker work down there and this happen without notice. I know for sure third rail is turn off. Link to comment Share on other sites More sharing options...
6 Lexington Ave Posted April 5, 2012 Author Share #363 Posted April 5, 2012 http://mta.info/mta/news/releases/?en=120404-NYCT1 Link to comment Share on other sites More sharing options...
m7zanr160s Posted April 6, 2012 Share #364 Posted April 6, 2012 I like this new way of maintenance. It's about time. Link to comment Share on other sites More sharing options...
N4 Via Merrick Rd Posted April 6, 2012 Share #365 Posted April 6, 2012 As part of the ongoing FasTrack project, from April 7th to the 16th, there will be no Manhattan-bound E- or F-line service at Sutphin Blvd (Hillside only), Briarwood-Van Wyck Blvd and 75 Av. Manhattan-bound trains will run express between Parsons Blvd or Jamaica-Van Wyck and Forest Hills-71 Av at all times during this service change. that's not a Fastrack the whole QBL or the Hillside Line would not be in service at all. Link to comment Share on other sites More sharing options...
N4 Via Merrick Rd Posted April 6, 2012 Share #366 Posted April 6, 2012 i hope they fix up those problems at South Ferry like in the photos shown in the topic "My Tax Dollars" since the SF branch will be apart of Fastrack Link to comment Share on other sites More sharing options...
N4 Via Merrick Rd Posted April 8, 2012 Share #367 Posted April 8, 2012 b4 any1 asks: why did the Broadway Line not get a FASTRACK? Answer 1: All the station are already renovated and in good shape Answer 2: almost every weekend theres a G/O Answer 3: other Line Structure are in good shape from G/Os and also the lighting(CFLs) is at its best. there you go DO NOT ASK why the Broadway Line did not get a FASTRACK Because that answers it. Link to comment Share on other sites More sharing options...
Wallyhorse Posted April 9, 2012 Share #368 Posted April 9, 2012 They need 5 car markers on the Eastern Div. (Nassau) for that. They really should do that, as it would allow flexibility, such as resuming the Banker's specials, but using CI equipment instead of bringing ENY equipment back over. That might very well work since you probably would only need five cars for the "Bankers Specials" instead of even eight, with such trains in the overnights also being available to use during those hours on the regular route when ridership is lower (especially if R160s are used). Link to comment Share on other sites More sharing options...
pjbr40 Posted April 9, 2012 Share #369 Posted April 9, 2012 IMO i just realized something. I know what is Fasttrak. To me i think this Fasttrak is another way of how the MTA got in repairs and maintenance again like they did back in the 1980/ Remember this is IMO Link to comment Share on other sites More sharing options...
East New York Posted April 11, 2012 Share #370 Posted April 11, 2012 I must say that this weeks FastTrack has been quite different than anything I have seen. For one, all the signs are actually incorrect. There is no Train service in Brooklyn at all. Now what I love is the fact that trains run to Flatbush Avenue all night! That was a welcome treat to see a Flatbust Avenue bound Express train pullin in to my stop in the Bronx at 2:15 this morning. Now if only thr 5 ran to Flatbush all the time!! Link to comment Share on other sites More sharing options...
Brighton Express Posted April 11, 2012 Share #371 Posted April 11, 2012 I have heard some rumors about FastTrack testing on the Park Slope/Viaduct Express. Is it true, or just another to 9th Av? Link to comment Share on other sites More sharing options...
mark1447 Posted April 12, 2012 Share #372 Posted April 12, 2012 The only official Fastracks I will call Fastrack is the ones the MTA mark as Fastrack. Any other G/O as most people claim as "Fastrack" i don't consider it, only a standard General Order.... Just like most are saying the and bypassing stops in Queens. To me it is Standard G/O not Fastrack.. Link to comment Share on other sites More sharing options...
N6 Limited Posted April 12, 2012 Share #373 Posted April 12, 2012 The only official Fastracks I will call Fastrack is the ones the MTA mark as Fastrack. Any other G/O as most people claim as "Fastrack" i don't consider it, only a standard General Order.... Just like most are saying the and bypassing stops in Queens. To me it is Standard G/O not Fastrack.. It's actually not a standard go, it'sa differnt program funded with the same money as FastTrack. Link to comment Share on other sites More sharing options...
Amtrak7 Posted April 12, 2012 Share #374 Posted April 12, 2012 I have heard some rumors about FastTrack testing on the Park Slope/Viaduct Express. Is it true, or just another to 9th Av? There are only two other "fake FASTRACK" runs programmed for this year: - Wakefield 241 St-Nereid Av - Bay Pkwy-Stillwell Both of these will be two week 24/7 all track shutdowns. Link to comment Share on other sites More sharing options...
NX Express Posted April 12, 2012 Share #375 Posted April 12, 2012 Will Nereid Av handle all of the and trains? Link to comment Share on other sites More sharing options...